Neolex
  • Legal
    • Acts
    • Regulations
    • Circulars
    • Master Circulars
    • Others
      • Rules
      • General Orders
      • Guidelines
      • Guidance Notes
  • Chatbot
    • Amendments
    • Policy Proposal
    • Knowledge Base
  • Orders
    • Chairperson / WTM Orders
    • QJA Orders
    • AO Orders
    • SAT Orders
    • Court Orders
    • Obligations
    • NISM
Corpus updated on 15 November 2026
Manoj Arora
  • About Neolex
  • About Manoj
  • Contact Me

Orders

  • Chairperson / WTM Orders1,359
  • QJA Orders190
  • AO Orders1,477
  • SAT Orders272
  • Court Orders282

Cases › Appeals to SAT › Appeal No. 387 of 2025

India Asset Growth Fund-II and Anr. v. Securities and Exchange Board of India

Appeal No. 387 of 2025lodged as Appeal (L) No. 386 of 2025under section 15T of SEBI Act, 1992disposed of

Partly allowed on 17 March 2026.

Parties

Appellants India Asset Growth Fund-II and Anr.

Respondents Securities and Exchange Board of India

Order appealed against

  • Adjudication Order in the matter of India Asset Growth Fund II · 3 July 2025

Orders of the Tribunal 7

  1. 13 August 2025

    mentionedadjourned not on board

    Not on Board. Learned Advocate for the appellant mentioned the matter for urgent listing. Call on 18.08.2025.

    Next: 18 August 2025

  2. 18 August 2025

    admittedstay granted 50%time for replytime for rejoinderadjourned

    Admit. There shall be stay of recovery subject to deposit of 50% of the penalty within two weeks from today and same shall be kept in an interest bearing account. Respondent is allowed four weeks’ time to file reply. Rejoinder, if any, be filed within two weeks thereafter. By consent, call on October 17, 2025 alongwith Appeal No. 355 of 2025.

    Next: 17 October 2025

  3. 17 October 2025

    application allowedtime for replyadjourned

    The Misc. Application Nos. 883, 966 and 965 for exemption are allowed and stands disposed of. Learned Advocate for the Respondent seeks four weeks time to file reply. Granted. Call on January 14, 2026.

    Next: 14 January 2026

    Heard with 3 other appeals

  4. 14 January 2026

    adjourned

    Learned Advocate for the appellant seeks time.

    Next: 11 March 2026

    Heard with 3 other appeals

  5. 11 March 2026

    adjourned

    Adjournment is sought by the appellants.

    Next: 16 April 2026 at 2:30 p.m.

    Heard with 3 other appeals

  6. 16 March 2026

    part heard

    Heard in part.

    Next: 17 March 2026

    Heard with 3 other appeals

  7. 17 March 2026

    appeal partly allowedapplication disposed of

    Appeal Nos.355 and 387 of 2025 filed by the `Fund' and the `Fund Manager' are allowed in part and Orders dated June 20, 2025 and July 3, 2025 are modified. The orders … are set aside qua the Fund. The entire penalty of 24 Lakh under Sections 15C and 15EA shall be paid by the Fund Manager (Appellant No.2). Pending interlocutory application(s), if any, stand disposed of.

    The order, read as a record

    Heard with 3 other appeals

The Tribunal's 2026 orders, read and not yet reviewed; orders of earlier years are not held.