SEBI's investigation into the trading and off-market transfers in the shares of Indo Pacific Software and Entertainment Ltd. in 2007: the adjudicating officer's orders of February 2012 against entities that transferred shares off market and did not comply with the investigating authority's summons, and the Securities Appellate Tribunal's order on their appeals (Bharat Shantilal Thakkar and others, 2012).
Orders 4
- 29 February 2012Adjudication order against Shri Bhavesh Prakash Pabari in the matter of Indo Pacific Software and Entertainment Ltd
Securities and Exchange Board of India: Adjudicating Officer · Final order · Penalty · penalties ₹6.5 lakh
parallel proceeding Adjudication order against Shri Bharat Shantilal Thakkar in the matter of Indo Pacific Software and Entertainment Ltd
parallel proceeding Adjudication order against Shri Hemant Madhusudan Sheth in the matter of Indo Pacific Software and Entertainment Ltd
parallel proceeding Adjudication order against Shri Prem Mohanlal Parikh in the matter of Indo Pacific Software and Entertainment Ltd
- 29 February 2012Adjudication order against Shri Prem Mohanlal Parikh in the matter of Indo Pacific Software and Entertainment Ltd
Securities and Exchange Board of India: Adjudicating Officer · Final order · Penalty · penalties ₹5.5 lakh
- 29 February 2012Adjudication order against Shri Hemant Madhusudan Sheth in the matter of Indo Pacific Software and Entertainment Ltd
Securities and Exchange Board of India: Adjudicating Officer · Final order · Penalty · penalties ₹5.5 lakh
parallel proceeding Adjudication order against Shri Prem Mohanlal Parikh in the matter of Indo Pacific Software and Entertainment Ltd
parallel proceeding Adjudication order against Shri Bharat Shantilal Thakkar in the matter of Indo Pacific Software and Entertainment Ltd
- 29 February 2012Adjudication order against Shri Bharat Shantilal Thakkar in the matter of Indo Pacific Software and Entertainment Ltd
Securities and Exchange Board of India: Adjudicating Officer · Final order · Penalty · penalties ₹5 lakh
parallel proceeding Adjudication order against Shri Prem Mohanlal Parikh in the matter of Indo Pacific Software and Entertainment Ltd
Chronology
- 8 January 2010 investigation — Bhavesh Prakash Pabari — Summons issued by the investigating authority seeking details of the Noticee's off-market transactions
- 12 January 2010 reply — Bhavesh Prakash Pabari — The Noticee's reply to the summons of January 8, 2010
- 14 January 2010 reply — Hemant Madhusudan Sheth — The Noticee's reply to the summons of January 8, 2010
- 15 January 2010 reply — Bharat Shantilal Thakkar — The Noticee's reply to the summons of January 8, 2010
- 17 January 2010 reply — Prem Mohanlal Parikh — The Noticee's reply to the summons of January 8, 2010
- 17 May 2010 investigation — Hemant Madhusudan Sheth — Further summons asking the Noticee to submit further information and appear personally before the investigating authority
- 17 June 2010 investigation — Bhavesh Prakash Pabari — Further summons asking the Noticee to submit further information and appear personally before the investigating authority
- 1 July 2010 reply — Bharat Shantilal Thakkar — The Noticee said he needed more time to collect the documents
- 5 July 2010 reply — Bhavesh Prakash Pabari — The Noticee said he had already replied and needed at least 4 weeks to collect the documents
- 6 July 2010 reply — Prem Mohanlal Parikh — The Noticee asked for one month's extension
- 7 July 2010 reply — Hemant Madhusudan Sheth — The Noticee said he had already replied and needed at least 45 days to collect the documents
- 9 July 2010 investigation — Bhavesh Prakash Pabari — The investigating authority granted 10 days' extension and asked the Noticee to appear on July 20, 2010
- 12 July 2010 investigation — Prem Mohanlal Parikh — The investigating authority granted an extension and asked the Noticee to appear on July 21, 2010
- 17 July 2010 reply — Hemant Madhusudan Sheth — The Noticee asked for 45 more days; no further reply or documents were submitted
- 19 July 2010 reply — Bhavesh Prakash Pabari — The Noticee said he was annexing his bank statement and sought 3 more weeks; no further reply or documents were submitted
- 21 July 2010 reply — Prem Mohanlal Parikh — The Noticee asked for 30 more days; no further reply or documents were submitted
- 17 January 2011 appointment — Adjudicating officer appointed under rule 3 of the Adjudication Rules and rule 3 of the SCR Rules
- 4 July 2011 show cause notice — Bhavesh Prakash Pabari
- 23 July 2011 reply — Hemant Madhusudan Sheth — Reply to the show cause notice (received on August 17, 2011)
- 4 August 2011 reply — Bhavesh Prakash Pabari — Reply to the show cause notice (received on August 17, 2011)
- 22 August 2011 adjournment — Bhavesh Prakash Pabari — Hearing adjourned at the request of the Noticee's representatives
- 23 August 2011 adjournment — Prem Mohanlal Parikh — Hearing adjourned at the request of the Noticee's representatives
- 4 November 2011 hearing — Bhavesh Prakash Pabari — Hearing attended by the Noticee's advocate, after a corrigendum to the appointment order and to the show cause notice
- 11 November 2011 written submission — Bhavesh Prakash Pabari
- 31 January 2012 other — Bhavesh Prakash Pabari — Hearing notice clarifying that all relevant documents had been provided, with an opportunity to appear or make submissions by February 10, 2012
- 6 February 2012 reply — Bhavesh Prakash Pabari — The Noticee again sought copies of the same documents and information
- 29 February 2012 Adjudication order against Shri Bhavesh Prakash Pabari in the matter of Indo Pacific Software and Entertainment Ltd
- 29 February 2012 Adjudication order against Shri Prem Mohanlal Parikh in the matter of Indo Pacific Software and Entertainment Ltd
- 29 February 2012 Adjudication order against Shri Hemant Madhusudan Sheth in the matter of Indo Pacific Software and Entertainment Ltd
- 29 February 2012 Adjudication order against Shri Bharat Shantilal Thakkar in the matter of Indo Pacific Software and Entertainment Ltd