Neolex
  • Legal
    • Acts
    • Regulations
    • Circulars
    • Master Circulars
    • Others
      • Rules
      • General Orders
      • Guidelines
      • Guidance Notes
  • Chatbot
    • Amendments
    • Policy Proposal
    • Knowledge Base
  • Orders
    • Chairperson / WTM Orders
    • QJA Orders
    • AO Orders
    • SAT Orders
    • Court Orders
    • Obligations
    • NISM
Corpus updated on 15 November 2026
Manoj Arora
  • About Neolex
  • About Manoj
  • Contact Me

Orders

  • Chairperson / WTM Orders1,359
  • QJA Orders190
  • AO Orders1,477
  • SAT Orders272
  • Court Orders282

Cases › Securities Appellate Tribunal

C & C Constructions Limited v. Bombay Stock Exchange

Judgment 31 August 2026, MumbaiProceeding AppealBy P. S. Dinesh Kumar, Meera Swarup, Dheeraj Bhatnagar, coram: justice p. s. dinesh kumar, presiding officer; ms. meera swarup, technical member; dr. dheeraj bhatnagar, technical memberCase Appeal No. 136 of 2021Outcome allowed

Read from the order by machine and checked against it; not yet reviewed by a person. The order itself is the authority.

Case history

Latest order held Judgment, 31 August 2026Appeal known — on appeal from 28 June 2019; decided on appeal 31 August 2026

  1. 28 June 2019THE ORDER DATED 28.06.2019 PASSED BY THE BSE · named in an order held; not yet held in Neolex
  2. 31 August 2026C & C Constructions Limited v. Bombay Stock Exchange (this order) · Securities Appellate Tribunal · Judgment

C & C Constructions Limited appealed under section 15T of the SEBI Act against the BSE's order of June 28, 2019 and challenged the fines that BSE and the National Stock Exchange had levied on it under their Standard Operating Procedure, for a period when the moratorium of its insolvency resolution process was in force. It was admitted that both exchanges had filed their claims in the insolvency resolution process, and that no proceeds had been received; the company, its advocate said, had been sold on an "as is where is" basis as a going concern. The Tribunal held that, this position having attained finality, the exchanges' claims had been rendered unenforceable, so that their suggestion that the company apply for a waiver was superfluous. The exchanges' demands were quashed and the appeal allowed.

Appeals decided

  1. Appeal No. 136 of 2021 — allowed

    C & C Constructions Limited v. Bombay Stock Exchange; National Stock Exchange of India Limited

    Against THE ORDER DATED 28.06.2019 PASSED BY THE BSE

    Against The SOP (Standard Operating Procedure) fines levied by the respondent Exchanges

    In the circumstances, the demands raised by the respondent Exchanges are unsustainable and accordingly they are quashed.

    In the circumstances, the demands raised by the respondent Exchanges are unsustainable and accordingly they are quashed.

Issues

Whether the exchanges' SOP fines for the period of the moratorium can be enforced against the company after its insolvency resolution process, or whether it must apply for a waiver
No: the exchanges filed their claims in the insolvency resolution process and received nothing, a position that has attained finality, so their claims are unenforceable and a waiver application is superfluous; the demands are quashed

What it holds

  1. [On an exchange's SOP fines for the period of a moratorium, when its claim was filed in the insolvency resolution process] Admitted position is, respondents filed their claims in the insolvency resolution process and no proceeds have been received and this factual matrix has attained finality. Resultantly, respondents' claims have been rendered unenforceable. Therefore, the submissions made on behalf of the respondents suggesting the appellant to file waiver applications are superfluous. ratio para 5

Other orders

  • appeal from THE ORDER DATED 28.06.2019 PASSED BY THE BSE

Sources

  • the Tribunal's order as published on its website; the link it gives is valid for one session only, so none is kept (read 15 October 2026)