Neolex
  • Legal
    • Acts
    • Regulations
    • Circulars
    • Master Circulars
    • Others
      • Rules
      • General Orders
      • Guidelines
      • Guidance Notes
  • Chatbot
    • Amendments
    • Policy Proposal
    • Knowledge Base
  • Orders
    • Chairperson / WTM Orders
    • QJA Orders
    • AO Orders
    • SAT Orders
    • Court Orders
    • Obligations
    • NISM
Corpus updated on 15 November 2026
Manoj Arora
  • About Neolex
  • About Manoj
  • Contact Me

Orders

  • Chairperson / WTM Orders1,359
  • QJA Orders190
  • AO Orders1,477
  • SAT Orders272
  • Court Orders282

Cases › Securities and Exchange Board of India: Chairperson and Whole-Time Members › In the matter of Urban Infrastructure Venture Capital Fund

Final Order in the matter of Urban Infrastructure Venture Capital Fund

Final order 31 October 2022, MumbaiProceeding Directions (sections 11 and 11B)By S. K. Mohanty, whole time memberOrder no. WTM/SM/AFD-1/AFD-1-SEC/20965/2022-23Outcome directions issuedRead the order (PDF)

Read from the order by machine and checked against it; not yet reviewed by a person. The order itself is the authority.

Case history

Latest order held Final order, 31 October 2022Appeal none known to Neolex

  1. 31 October 2022Final Order in the matter of Urban Infrastructure Venture Capital Fund (this order) · Securities and Exchange Board of India: Chairperson and Whole-Time Members · Final order

Urban Infrastructure Venture Capital Fund (registered as a venture capital fund in 2006) ran one close-ended real estate scheme, Urban Infrastructure Opportunities Fund, with a corpus of Rs. 2,434 crore, whose term under its placement memorandum (7 years plus two one-year extensions) ended on June 8, 2015; the trustee (Urban Infrastructure Trustees Limited) and the investment manager (Urban Infrastructure Venture Capital Limited) extended it with the consent of about 76.63% of the investors and had still not wound it up in 2022. SEBI's Whole Time Member held that the contents of a placement memorandum are confined to those listed in regulation 17(1) of the VCF Regulations, that the term could not be extended further by the unit holders' consent, and that commercial hardship in selling illiquid investments is no excuse for not winding up under regulations 23(1)(a) and 24(2); the fund was also found to have delayed its response to a SCORES complaint in breach of SEBI's circular of December 18, 2014. The trustee, the investment manager and their directors were held liable (the proceedings against R.A. Agarwal, who had died, abated) and were directed to wind up the scheme within 3 months (by January 31, 2023) through two independent valuations, an in-specie option and an exit at NAV, and to file a CA-certified report; the directors were restrained for 1 year from raising money from the public, and all the Noticees were barred for 1 year from associating with SEBI-registered intermediaries and funds.

Noticees

No.NameCapacityPAN / registrationOutcome for them
1.Urban Infrastructure Trustees LimitedtrusteeAAACU8060F
2.P.K. Bansaldirector of Urban Infrastructure Trustees LimitedAAIPB1934G
3.Sandeep Kediadirector of Urban Infrastructure Trustees LimitedABEPK6716C
4.Jesal Sanghvidirector of Urban Infrastructure Trustees LimitedANYPS0872P
5.R.A. Agarwaldirector of Urban Infrastructure Trustees LimitedAAMPA9291Kabated (Noticee No. 5 passed away on January 27, 2017; the proceedings against him abated (para 36))
6.Dharmesh Trivediadditional director of Urban Infrastructure Trustees LimitedAABPT5910F
7.Urban Infrastructure Venture Capital Limitedinvestment manager, settlorAAACU8061E
8.Parag Parekhmanaging director, ceo of Urban Infrastructure Venture Capital LimitedAAGPP4440H
9.Anand Jaindirector of Urban Infrastructure Venture Capital LimitedAABPJ1890J
10.P Krishnamurthydirector of Urban Infrastructure Venture Capital LimitedAIYPK0416E
11.Rajeev Bhandaridirector of Urban Infrastructure Venture Capital LimitedAAQPB8956N
12.S S Thakurdirector of Urban Infrastructure Venture Capital LimitedAABPT5854A

Charges

  1. “the Fund has failed to wind up the Scheme as per regulation 24(2) read with regulation 23(1)(a) of VCF Regulations which has led to violation of regulation 23(1)(a) of VCF Regulations”

    Provisions regulation 23(1)(a) of the SEBI (Venture Capital Funds) Regulations, 1996; regulation 24(2) of the SEBI (Venture Capital Funds) Regulations, 1996 — as on 8 June 2015

    Found Urban Infrastructure Trustees Limited: established; P.K. Bansal: established; Sandeep Kedia: established; Jesal Sanghvi: established; Dharmesh Trivedi: established; Urban Infrastructure Venture Capital Limited: established; Parag Parekh: established; Anand Jain: established; P Krishnamurthy: established; Rajeev Bhandari: established; S S Thakur: established; R.A. Agarwal: abated

  2. “the Fund has violated the provisions of SEBI circular CIR/OIAE/1/2014 dated December 18, 2014 in so far as it has not been able to promptly respond to and timely redress the investor complaint”

    Provisions SEBI circular CIR/OIAE/1/2014 dated December 18, 2014 (SCORES), paragraphs 9, 12 and 13 — as on 31 March 2020

    Found Urban Infrastructure Trustees Limited: established; P.K. Bansal: established; Sandeep Kedia: established; Jesal Sanghvi: established; Dharmesh Trivedi: established; Urban Infrastructure Venture Capital Limited: established; Parag Parekh: established; Anand Jain: established; P Krishnamurthy: established; Rajeev Bhandari: established; S S Thakur: established; R.A. Agarwal: abated

Directions

  1. Compliance directions — 3 months from the date of this Order until latest by January 31, 2023 — Urban Infrastructure Trustees Limited, P.K. Bansal, Sandeep Kedia, Jesal Sanghvi, Dharmesh Trivedi, Urban Infrastructure Venture Capital Limited, Parag Parekh, Anand Jain, P Krishnamurthy, Rajeev Bhandari and S S Thakur

    “Noticees (except for Noticee No. 5) shall ensure that the Scheme of the Fund is wound up by providing exit to its investors / unit holders within a maximum period of 3 months from the date of this Order in the following manner: Two separate valuations of all the remaining assets of the Scheme of the Fund (as on October 31, 2022) shall be obtained from two independent reputed valuers; The NAV of the Scheme … shall be determined … by adopting higher of the valuation …; Exit to the investors shall be provided first, by offering an option … to take exit by way of in specie distribution …; The investors / unit holders who do not exercise their option for in specie distribution, shall be given exit on the basis of the NAV … shall be completed within a maximum period of 3 months from the date of this Order i.e. latest by January 31, 2023.” (para 37.1)

  2. Compliance directions — until by February 21, 2023 — Urban Infrastructure Trustees Limited, P.K. Bansal, Sandeep Kedia, Jesal Sanghvi, Dharmesh Trivedi, Urban Infrastructure Venture Capital Limited, Parag Parekh, Anand Jain, P Krishnamurthy, Rajeev Bhandari and S S Thakur

    “The Noticees (except for Noticee No. 5) shall file a report certified by a CA declaring that all the investors of the Scheme have been provided an exit and the Scheme of Fund stands wound up. The said report shall be filed within a period of three weeks after completion of the exit and repayment to the investors/unit holders of the Scheme i.e. by February 21, 2023.” (para 37.2)

  3. Barred from an activity — 1 year from the date of this Order — issuing prospectus, offer document or advertisement soliciting money from the public — P.K. Bansal, Sandeep Kedia, Jesal Sanghvi, Dharmesh Trivedi, Parag Parekh, Anand Jain, P Krishnamurthy, Rajeev Bhandari and S S Thakur

    “Noticees No. 2 to 4, 6 and 8 to 12 are hereby restrained from accessing the securities market by issuing prospectus, offer document or advertisement soliciting money from the public in any manner, either directly or indirectly, for a period of 1 year from the date of this Order.” (para 37.3)

  4. Barred from association — 1 year from the date of this Order — Urban Infrastructure Trustees Limited, P.K. Bansal, Sandeep Kedia, Jesal Sanghvi, Dharmesh Trivedi, Urban Infrastructure Venture Capital Limited, Parag Parekh, Anand Jain, P Krishnamurthy, Rajeev Bhandari and S S Thakur

    “Noticees No. 1 to 4, and 6 to 12 are hereby restrained from associating themselves, directly or indirectly with any SEBI registered intermediaries including SEBI registered funds such as Mutual Funds, Alternative Investment Funds, Portfolio Management Services etc. which deal with investors’ money in any manner for a period of 1 year from the date of this Order.” (para 37.4)

  5. Proceedings abated — R.A. Agarwal

    “Noticee No. 5, Mr. R A Agarwal has passed away. Therefore, the extant proceedings against him stands abated.” (para 36)

Issues

Whether the Scheme of the Fund has been wound up as per the terms and conditions and the period of maturity as mentioned in the PPM
No: its term ended on June 8, 2015; the further extension on the investors' consent was not permissible, and the scheme was not wound up
If not, whether the conduct of the Noticees violated the VCF Regulations and SEBI circular dated December 18, 2014, warranting directions under Section 11B(1) of the SEBI Act read with regulations 29(c) and (d) of the VCF Regulations
Yes: regulation 23(1)(a) read with 24(2) of the VCF Regulations and the SCORES circular were violated; directions issued

What it holds

  1. the contents of a Placement Memorandum cannot be different from what has been mentioned under regulation 17 (1) of VCF Regulations. Therefore, when regulation 17 (1) of VCF Regulations does not provide for making any amendment of the period of operation of the Fund, once the period of maturity has been fixed including the extension of period of maturity of the Fund (i.e. two extensions of one year each) as specifically provided under the Regulation, it is not open for the Trustees or the Investment Manager of the Fund to further extend the period of maturity of Fund by taking the consent of the unit holders / beneficiaries. … Once the period of maturity as declared in the Fund’s PPM is over, the Fund has to compulsorily wind up the Scheme under regulation 23 of the VCF Regulations. ratio paras 14-15

  2. There is no denying the fact that being a beneficiary to the Scheme of the Fund, does give some rights to the unit holder of the Scheme, but the same cannot be stretched to mean that it also gives a right to the unit holders to alter the very material document of the Fund, especially when the VCF Regulations do not give any such right to the unit holders of a Scheme floated by a VCF. ratio para 16

  3. in view of the express provision of regulation 24(2) read with regulation 23(1)(a) of VCF Regulations, the inability as shown by the Scheme of the Fund to wind up cannot be taken as a reason to continue the Scheme beyond the period specified in PPM read with the VCF Regulations. … It is not a case of force majeure but rather economic / financial hardship. … I find that avoidance of loss cannot be a valid ground for not complying with the mandatory obligation prescribed under VCF Regulations with respect to winding up of the Scheme of the Fund at the expiry of its term. ratio paras 18-19

  4. it may not be an appropriate interpretation of the law to state that a scheme that has invited investors to invest in the fund promising it to have a definite lifespan, can be permitted to continue to exist in perpetuity only on the ground that any exit that may be provided to the unit holders, may not be profitable to them at the time of their exit. ratio para 20

  5. if the submission of the Noticees has to be considered as tenable, it will tantamount to reading the word “working” in the aforesaid SEBI circular … not redressing the investor grievance within the timeline prescribed under the aforesaid circular is a separate and distinct violation from the violation involving non-winding up of the Scheme of the Fund. ratio paras 27-28

  6. all the acts which are executed in the name of an incorporated entity, are done by the natural persons who by their own minds and wisdom, are controlling the affairs and management of such an artificial juristic person (company) in the capacity of its Directors. … Therefore, the Director cannot wriggle out from his / her liability arising out of any wrongdoing by the company. ratio paras 32-34

Chronology

  1. 25 August 2015 other — SEBI intimated of the investors' approval to extend the scheme's term to December 31, 2016
  2. 7 June 2021 show cause notice — Urban Infrastructure Trustees Limited, P.K. Bansal, Sandeep Kedia, Jesal Sanghvi, R.A. Agarwal, Dharmesh Trivedi, Urban Infrastructure Venture Capital Limited, Parag Parekh, Anand Jain, P Krishnamurthy, Rajeev Bhandari and S S Thakur — Common show cause notice after an inspection completed in February 2021
  3. 25 June 2021 reply — Urban Infrastructure Trustees Limited and Urban Infrastructure Venture Capital Limited — Common reply of UIVCL and UITL
  4. 22 March 2022 other — Urban Infrastructure Trustees Limited, P.K. Bansal, Sandeep Kedia, Jesal Sanghvi, R.A. Agarwal, Dharmesh Trivedi, Urban Infrastructure Venture Capital Limited, Parag Parekh, Anand Jain, P Krishnamurthy, Rajeev Bhandari and S S Thakur — SEBI's email seeking further information
  5. 15 April 2022 reply — Urban Infrastructure Trustees Limited, P.K. Bansal, Sandeep Kedia, Jesal Sanghvi, R.A. Agarwal, Dharmesh Trivedi, Urban Infrastructure Venture Capital Limited, Parag Parekh, Anand Jain, P Krishnamurthy, Rajeev Bhandari and S S Thakur
  6. 4 October 2022 written submission — Urban Infrastructure Trustees Limited, P.K. Bansal, Sandeep Kedia, Jesal Sanghvi, R.A. Agarwal, Dharmesh Trivedi, Urban Infrastructure Venture Capital Limited, Parag Parekh, Anand Jain, P Krishnamurthy, Rajeev Bhandari and S S Thakur
  7. 6 October 2022 hearing — Urban Infrastructure Trustees Limited, P.K. Bansal, Sandeep Kedia, Jesal Sanghvi, R.A. Agarwal, Dharmesh Trivedi, Urban Infrastructure Venture Capital Limited, Parag Parekh, Anand Jain, P Krishnamurthy, Rajeev Bhandari and S S Thakur — Represented by Mr. Ravi Kadam, Senior Advocate and AZB & Partners
  8. 11 October 2022 written submission — Urban Infrastructure Trustees Limited, P.K. Bansal, Sandeep Kedia, Jesal Sanghvi, R.A. Agarwal, Dharmesh Trivedi, Urban Infrastructure Venture Capital Limited, Parag Parekh, Anand Jain, P Krishnamurthy, Rajeev Bhandari and S S Thakur — Shareholders' agreements with restrictive clauses on transfer submitted
  9. 18 October 2022 written submission — Urban Infrastructure Trustees Limited, P.K. Bansal, Sandeep Kedia, Jesal Sanghvi, R.A. Agarwal, Dharmesh Trivedi, Urban Infrastructure Venture Capital Limited, Parag Parekh, Anand Jain, P Krishnamurthy, Rajeev Bhandari and S S Thakur — Answers to SEBI's questions of October 12, 2022

Other orders

  • cites it Order in respect of Cinema Capital Venture Fund 30 April 2025

Precedents cited

  • Balaji General Stores vs. Deputy Commissioner of Commercial Taxes, Hon'ble High Court of Andhra Pradesh, decided on December 19, 1986 — invoked by the authority, applied: The word "namely" is restrictive: the general expression before it is confined to the items that follow
  • Narmada Bachao Andolan and Ors. vs. State of Madhya Pradesh and Ors. MANU/SC/0599/2011 — invoked by the authority, distinguished: Impossibility of performance (lex non cogit ad impossibilia) excuses a statutory duty; economic hardship is not impossibility
  • Cinema Capital Advisory Private Limited et. al. vs. SEBI and other connected appeal, Hon'ble SAT, decided on September 14, 2021 — invoked by the authority, relied: Even if regulations 23 and 24 of the VCF Regulations are directory, a scheme must be wound up and its proceeds distributed at the earliest
  • Delhi Airport Metro Express Pvt. Ltd. vs. Delhi Metro Rail Corporation, Hon'ble Supreme Court, decided on May 5, 2022 — invoked by the authority, applied: Effect must be given to plain words; words may not be added ("working" days)